Official recordStatewidePower
EVENT August 31, 2026 · VERIFIED August 31, 2026
ERCOT's Batch Zero eligibility deadline arrives
ERCOT's published schedule required corrected dynamic-model information by August 31. Projects with unresolved deficiencies may be ineligible for the first statewide large-load batch study.
WHY IT MATTERSThe eligibility gate helps separate serious, document-supported projects from the much larger pool of preliminary requests.
Open primary source ↗ERCOT · July 29 grid presentationOfficial recordStatewideMarket
EVENT July 29, 2026 · VERIFIED August 31, 2026
ERCOT reports approximately 474 GW of large-load requests
ERCOT reported that roughly 90% of approximately 474 GW seeking large-load interconnection was associated with data centers as of June 2026.
WHY IT MATTERSThe figure describes requests—not completed projects—but demonstrates the extraordinary scale of Texas demand and the need for disciplined project verification.
Open primary source ↗ERCOT · Texas Senate presentationOfficial recordStatewideRegulation
EVENT June 18, 2026 · VERIFIED August 31, 2026
PUCT approves ERCOT's first batch process for large users
The approved framework studies qualified projects of 75 MW or more together, identifies transmission needs and creates options involving onsite generation or controllable demand.
WHY IT MATTERSTexas has moved from project-by-project review toward a statewide reliability process that can materially affect project timing and location.
Open primary source ↗ERCOT · Official news releaseOfficial sourceStatewideWater & permits
EVENT March 11, 2026 · VERIFIED August 31, 2026
TCEQ centralizes access to pending permit information
TCEQ's permit-status resources provide direct access to pending and completed air, wastewater, stormwater and water-supply matters relevant to industrial development.
WHY IT MATTERSEnvironmental filings can reveal infrastructure requirements and project movement before a campus is broadly announced.
Open primary source ↗TCEQ · Permit status resources