Air registration · Hunt County

TCEQ acknowledges Royse City data-center air registration

A November 17 TCEQ letter acknowledges a permit-by-rule emissions certification for the Royse City Data Center; it does not establish construction completion or operation.

Downtown Royse City, Texas, in December 2019
Downtown Royse City, December 25, 2019. Community-context image; it does not show the Hunt County data-center site or equipment covered by the November 2026 air action. Renelibrary, CC BY-SA 4.0, via Wikimedia Commons; unchanged.

What happened: The Texas Commission on Environmental Quality issued a final-action letter on November 17 acknowledging that BT Gateway Data Center, LLC certified emissions associated with the Royse City Data Center under Permit by Rule Registration 185291 and 30 TAC § 106.511. TCEQ identifies the regulated entity as RN112486717 at 4989 County Road 2656 near Royse City in Hunt County.

TCEQ · Permit by Rule Registration 185291 final action · November 17, 2026 · record metadata

What the letter establishes

The letter says TCEQ completed its ePermits review and acknowledged the emissions certification under the listed permit-by-rule provision. It requires the company to maintain compliance records and says permit holders must report each registration's operational status through STEERS by December 31 each year.

That is an environmental authorization record. It is not a finding that construction is complete, the equipment has been installed, the facility has energized or the data center is operating.

A separate filing describes the proposed building

A Texas Department of Licensing and Regulation registration dated June 23 describes a privately funded, 100,000-square-foot data center at the same address. It lists an estimated construction cost of $384 million and estimated work dates from August 1, 2026, through February 12, 2027.

TDLR · BT Gateway Data Center, TABS2026023619 · registered June 23, 2026

The square footage, cost and dates are filing estimates. The TDLR registration is an accessibility-project record, not proof of spending, construction progress, electrical capacity, occupancy or operation.

What remains missing

The public final-action letter reviewed for this edition does not include an equipment inventory, generating capacity, emissions table, water source, electric provider, utility commitments, measured use or an operating date. DataCentersTX did not send a records request before publication; the News Desk will first check for additional application and technical-review material as TCEQ posts the project file.

Why it matters to Texas readers

The action adds a project-specific environmental milestone to the earlier building registration. Keeping the two records separate prevents a common status error: an acknowledged air registration and a construction filing do not, by themselves, establish that a data center is built, energized or operating.

Useful next step: Use registration number 185291, project 414644 and regulated-entity number RN112486717 when checking later TCEQ records. The annual operational-status report due through STEERS is the next stated record that may help distinguish an authorized project from an operating facility.