Decision areaCurrent public positionStatus
Development applicationThe City overview, checked October 4, says no development application has been received for a data center within city limits.
OPEN Facility scale + phasingA filed building count, square footage, load and schedule are not established. The City-hosted developer Q&A contains projections, not an approved design.
OPEN Water + coolingThe City says it will not provide water to a data center using evaporative cooling. Project-specific demand still requires documentation.
PARTIAL Power deliveryA project-specific load, generation mix, transmission plan and customer-protection package are not established in the current public overview.
OPEN Sewer + dischargeA governing ordinance is adopted; any facility-specific discharge and pretreatment plan remains to be measured.
PARTIAL Incentives + obligationsJune 9 City statement: circulating terms were examples, not an agreement. A later executed agreement was not retrieved in this October 4 review.
OPEN Community benefitLocal hiring, training, procurement, infrastructure and enforcement commitments should be written, measurable and public.
TO BUILD Status labels are Data Centers Texas’ reading of the cited public record—not a City designation and not a judgment for or against a future project.