Corsicana / Navarro County

Riot energized the first 400 MW phase of its Corsicana campus and is evaluating AI and high-performance-computing uses for roughly 600 MW of remaining approved capacity.
Operating + evaluating AI expansionReviewed September 28, 2026

CURRENT PUBLIC SIGNAL

What we know now

Riot energized the first 400 MW phase of its Corsicana campus and is evaluating AI and high-performance-computing uses for roughly 600 MW of remaining approved capacity.

This is a working local record. Status reflects public announcements, filings, construction reports, and operating information available on the review date—not a guarantee that every proposed phase will be built.

State permit audit: Since September 21, 2026, TCEQ has paused data-center-related permit approvals while the ERCOT and Texas Water Development Board audits proceed. A filing, registration, or local approval does not establish that every required state authorization has been issued.

PROJECT SNAPSHOT

Corsicana Facility

Riot Platforms
400 MW operating / 600 MW under evaluation

The company halted the previously announced Phase II bitcoin-mining buildout while it evaluates AI/HPC development for the site's remaining power capacity.

WHAT COULD CHANGE THIS PAGE

Signals we’re watching

Data-center timelines move quickly. These are the next public signals most likely to clarify this community’s status.
  1. 01A new construction phase, lease, or energization milestone
  2. 02Hiring, vendor, or workforce-program announcements
  3. 03Utility, water, tax, or environmental reporting